East Side Paving & Drainage Improvement Project
To see important alerts regarding the East Side Paving and Drainage Improvement Project > CLICK HERE Version OptionsEast Side HeadlineBuffalo Speedway Project https://westutx.gov/1416/East-Side-Project-Alerts
To sign up to receive news and updates to the East Side Paving and Drainage Improvement Project > CLICK HEREBuffalo Speedway Project (choose to receive updates via email, text or both. Scroll down and select East Side Drainage Improvement)
Overview
In 2019, the City authorized the completion of a City Wide Drainage Modeling Study that evaluated and modeled existing conditions of the City's drainage system. The results indicated that the majority of the City has limited drainage capacity, with some areas having less than 2-year capacity. These findings indicated a need to improve the city's streets and drainage system.
Scope of Work
The East Side improvements are broken down into two packages:
- Package One (1) includes paving and drainage upgrades along University Boulevard from Buffalo Speedway to Kirby Drive.
- Package Two (2) includes paving and drainage upgrades along Wakeforest Avenue from Plumb Street to Pemberton Street, Rice from Wakeforest to Kirby Dr., and Duke Street from Buffalo Speedway to Wakeforest.
Project Timeline
2021
- January 22 - Official Notice to Proceed Issued to HDR Engineering, Inc., to complete the Preliminary Engineering Report.
- February 2 - Kick-off meeting held with City Staff and HDR.
- May 17 - Draft PER Review
- June 28 - City Council Workshop to discuss PER
- September 20 - City Council Workshop to discuss additional PER updates.
- October 20 - PER Completed
- November 15 - City Council accepted final PER.
- December 12 - Design Contract awarded to HDR Engineering
2022
- January 26 - Official "Kickoff" Meeting for design held with City Staff and HDR.
- March 28 - City Council Workshop to discuss traffic calming.
- July 25 - 75% Design update presented to City Council.
- August 29 - Public Townhall Meeting
2023
- March 29 - Public Townhall Meeting #2
- April - Tentative Project Construction Initiation of Package 1 (13-month duration)
- June - Estimated Package 2 Design completion
- Winter 2023 - Package 2 construction initiation (24-month duration)
Project Contacts
(For questions regarding the East Side Paving & Drainage Project, please contact City staff)
- City of West University Place - Public Works Department
- mailto:pwalters@westutx.gov Email Eduardo Barreto- Capital Projects Manager
- 713-662-5848 - (direct line)
- Email Danny Cameron- Public Works Director
- 713-662-5846 - (direct line)
- mailto:pwalters@westutx.gov Email Eduardo Barreto- Capital Projects Manager
- HDR Engineering
- John Peterson P.E. Project Manager