4/11/2025 - The contractor is on track to complete paving at the intersection of University Boulevard and Buffalo Speedway by the end of the day Saturday, April 12, weather permitting. At the same time, crews will return to the Sunset Boulevard and Buffalo Speedway intersection to perform minor repairs, also expected to be completed by end of day Saturday.
Starting Monday, April 14, Gulf Coast Pavers will begin Phase 4 of the project with the installation of a new crosswalk at W. Holcombe Boulevard. This phase is expected to be completed by April 22, weather permitting.
As work moves forward, traffic on Buffalo Speedway near W. Holcombe will be reduced to one lane in each direction (northbound and southbound). We encourage all residents and commuters to plan their routes accordingly and to continue driving with caution through the construction area.
We appreciate everyone’s patience and cooperation as we make steady progress on these important roadway improvements. Thank you for helping keep our community safe during construction.
------------------------------------------
4/3/2025 - Gulf Coast Pavers will complete Phase 3 of the Buffalo Speedway Paver Repair Project at the intersection of Rice Blvd. Inclement weather could delay completion of this intersection.
Weather permitting, on Saturday, April 5, Phase 2 will continue with work at the intersection of University Blvd., which is scheduled for completion by April 26. Once this phase is complete, the contractor will proceed to the final Phase, Phase 4 crosswalk at the intersection of W. Holcombe.
Temporary Traffic Control Measures:
Traffic control measures will be in effect throughout each phase of the project. Drivers and pedestrians are urged to exercise caution near work zones and follow all posted signs. We kindly ask drivers to plan their routes accordingly, as temporary delays may occur in these areas. Additionally, the City has coordinated alternative routes with METRO, aiming to minimize disruptions for riders and ensure efficient progress of the project.
If you have any questions about this project, please contact Capital Project Manager Eduardo Barreto at 713-662-5848 or by email at ebarreto@westutx.gov.
------------------------------------------
3/19/2025 - Effective today, March 19, Gulf Coast Pavers has initiated Phase 3 of the project to repair and replace the pavers at Rice Blvd. and Buffalo Speedway. As with the previous intersections, the contractor will begin at the crosswalks. The contractors will return to complete Phase 2 in the coming weeks.
Updated Phases and Schedule:
- Phase 2: Crosswalks and Intersection Logo
- Location: University Blvd. & Buffalo Speedway
- Duration: Estimated 6 weeks (Weather Permitting)
- Phase 3: Crosswalks and Intersection Logo
- Location: Rice Blvd. & Buffalo Speedway
- Duration: Estimated 6 weeks (Weather Permitting)
- Phase 4: Crosswalk at W. Holcombe Blvd.
- Duration: Estimated 2 weeks (Weather Permitting)
Temporary traffic control measures will be in effect during each phase. Drivers and pedestrians are urged to exercise caution near work zones and follow all posted signs. We kindly ask drivers to plan their routes accordingly, as temporary delays may occur in these areas.
If you have questions about this project, please contact Capital Project Manager Eduardo Barreto at 713-662-5848 or by email at ebarreto@westutx.gov
------------------------------------------
3/3/2025 - Beginning Monday, March 3 , Gulf Coast Pavers will be switching the Buffalo Speedway Paver Repair Project from the intersection at Sunset Blvd. to the intersection at University Blvd. As with the previous intersection at Sunset Blvd., the City’s contractor will begin at the crosswalks, and once completed, will move to the center of the respective intersection.
The updated work phases aim to improve workflow efficiency and minimize disruptions for residents.
Updated Phases and Schedule:
- Phase 2: Crosswalks and Intersection Logo
- Location: University Blvd. & Buffalo Speedway
- Duration: Estimated 6 weeks (Weather Permitting)
- Phase 3: Crosswalks and Intersection Logo
- Location: Rice Blvd. & Buffalo Speedway
- Duration: Estimated 6 weeks (Weather Permitting)
- Phase 4: Crosswalk at W. Holcombe Blvd.
- Duration: Estimated 2 weeks (Weather Permitting)
Temporary traffic control measures will be in effect during each phase. Drivers and pedestrians are urged to exercise caution near work zones and follow all posted signs. We kindly ask drivers to plan their routes accordingly, as temporary delays may occur in these areas.
If you have questions about this project, please contact Capital Project Manager Eduardo Barreto at 713-662-5848 or by email at ebarreto@westutx.gov
------------------------------------------
January 9, 2025 9 A.M.: Beginning January 13, Gulf Coast Pavers will begin phased repairs on the Buffalo Speedway brick paver crosswalks and intersection logos. The project is expected to last approximately 90 days, with work completed in three phases to minimize disruptions and ensure efficient progress.
Phase 1: Crosswalks on Buffalo Speedway (East and West)
- Locations: Sunset Blvd., Rice Blvd., and University Blvd.
- Work will start in the left-hand turn lane and move outward east and west to maintain consistent paver patterns.
- Duration: Estimated 3 weeks per location (Weather Permitting)
Phase 2: Intersection Crosswalks (North and South)
- Locations: Sunset Blvd., Rice Blvd., University Blvd., and W. Holcombe Blvd.
- Crews will work on intersection crosswalks while Buffalo Speedway remains open.
- Duration: Estimated 6 days per location (Weather Permitting)
Phase 3: Intersection Logos
- Locations: Sunset Blvd., Rice Blvd., and University Blvd.
- Work will occur in three stages: left-turn lanes, inner lanes, and outer lanes.
- Duration: Estimated 6 weeks per location (Weather Permitting)
Temporary traffic control measures will be in effect during each phase. Drivers and pedestrians should exercise caution near work zones and follow all posted signs. We kindly ask drivers to plan their routes accordingly, as temporary delays may occur in these areas.
If you have questions about this project, please contact Capital Projects Manager, Eduardo Barreto by email at ebarreto@westutx.gov or by phone at 713-662-5848.