This project will increase the size of the distribution line from the Wakeforest Water Plant into the City’s distribution system. These improvements will improve the pressure and flow throughout the water system.
Scope of Work
The project will include:
Approximately 1,410 linear feet of new 24-inch water line
Approximately 1,900 linear feet of new 16-inch water line
Approximately 800 linear feet of new 4-inch, 6-inch, 8-inch, and 12-inch water lines
Improvements at the Water Plant to connect the new lines
Distribution line improvements from the Wakeforest Water Plant to Bissonnet Street are within the City of Houston’s right-of-way and require approval from the City of Houston.
Schedule
2024
February 12 - City Council Approval for Design
February 26 - Design Process Begins
2025
February - August - Permitting Process
September - October - Final plans and contract documents